Compare office furniture quotations by matching each offer to the same BOQ revision, pricing unit, specification and delivery scope. Record deviations and missing costs before comparing totals. For UAE, Saudi Arabia and other GCC destinations, confirm who handles transport, receiving, assembly and after-sales work in writing.
Give every supplier the same comparison basis
Issue one dated BOQ with drawings, finish references, item quantities, destination city and required receiving date. Keep a clarification register and send approved changes to every bidder. A photograph can identify a design direction, but it does not establish the board core, hardware, dimensions or included accessories.
- Keep the BOQ item reference beside the supplier model and drawing revision.
- Ask the supplier to mark compliant, deviating or to confirm for each requirement.
- Separate base scope, priced alternatives and optional services so they are not silently substituted.
- Keep quotation validity, currency, payment milestones and any sample or tooling charges in the comparison.
Check whether the rate is per seat or per assembly
Illustrative quantity example: an office needs 100 employee positions. A quotation for 25 four-person bench assemblies and a quotation for 100 individual positions may describe the same seating capacity. Convert both to the same complete scope before comparing unit rates; do not multiply an assembly rate by the number of employees.
| Line to compare | What must match | What to clarify |
|---|---|---|
| Bench workstations | Employee positions, assembly count and layout | Whether frames, screens, cable trays and linking components are included |
| Executive desks | Desk, return, storage and left/right orientation | Whether a photographed side cabinet is part of the priced set |
| Meeting tables | Table size, sections, bases and cable openings | Power modules, AV equipment and site electrical work |
| Seating and storage | Individual pieces, upholstery, hardware and finish | Whether a package price includes every shown chair or cabinet |
Build a scope and cost reconciliation
Use a column for each offer, with one row for each included cost or responsibility. Add documented exclusions and buyer-side costs once. Mark an unknown cost as pending and request a current quotation; an empty cell must not make an incomplete offer look cheaper. Keep currency conversion assumptions and quotation dates visible.
| Comparison row | Record for every offer |
|---|---|
| Furniture and accessories | Specification revision, quantity, pricing unit, unit rate and extended total |
| Samples and drawings | Charge, approval reference, included revisions and release conditions |
| Packing and shipment | Packing method, packed volume/weight, freight scope, insurance and named destination |
| Import and onward transport | Named responsible party and separately confirmed destination charges |
| Receiving and assembly | Building access, unloading, floor delivery, fixing and packaging removal |
| Warranty and remedies | Covered components, exclusions, claim evidence, spares, freight and local labour |
Use the trade term and programme together
ICC Incoterms 2020 rules allocate buyer and seller costs, risks and obligations. Record the selected rule, version and named place or port, then list the destination services actually included in the offer. Ask the supplier and logistics provider to resolve scope gaps before award; a headline such as shipping included is insufficient for comparison.
Record separate milestones for drawing approval, finish or sample approval, production, inspection, corrective actions, shipment and site receiving. State what starts the production period and whether the buyer has a deadline for approvals. Ask whether the proposed programme fits the date the office needs usable furniture; production time alone does not establish that date.
Keep an evidence and deviation register
- Match every proposed item to the approved specification and record the supplier response to each open point.
- Request the relevant drawings, finish samples and model-specific supporting documents where the requirement calls for them.
- Agree inspection checks and the records needed before packing or shipment release.
- Identify who receives the order, records shortages or damage and handles replacement parts or site work.
- Obtain a revised written quotation covering accepted deviations, resolved costs and the agreed programme before placing the order.
Questions to send with the clarification request
- Which BOQ revision and drawings does this offer price?
- What is the pricing unit and which components are included in each set?
- Which specification deviations, unpriced services and destination responsibilities remain open?
- What approvals start production, and which milestones support the proposed receiving date?
- What warranty remedy is offered, and who pays parts, freight and destination labour?
Prepare a comparable RFQ for GulfForma
Send the same BOQ, selected references, quantities, finishes, destination and receiving requirements to GulfForma. Ask for a line-by-line response with deviations and exclusions so your team can reconcile it with other offers. Core panel furniture and partner-supplied categories should have their production route and inspection responsibility confirmed for the order. Local delivery, assembly and installation are included only when expressly agreed.
How this guide was prepared
Prepared as a procurement worksheet, not a survey of supplier prices or a completed project. The quantity example is illustrative. ICC supports the explanation of trade-term responsibilities; GulfForma resources are company-published planning tools. Obtain current written quotations and order-specific commitments.
Sources and related resources
- ICC: Incoterms 2020 — Official guidance on trade rules allocating costs, risks and obligations; identify the rule and named place or port in the offer.
- Furniture BOQ preparation and blank template — GulfForma planning resource for item references, quantities, specification fields and exclusions; not an independent supplier assessment.
- Pre-shipment QC guide and blank checklist — GulfForma inspection-planning resource; agree order-specific acceptance checks and evidence.
- Model and configuration selection guides — Company-published catalogue comparisons for dimensions, handed versions and assembly scope; confirm the selected order specification.
- Project sourcing and buyer deliverables — Company-published process and records; confirm the documents and services included for the actual order.