Office furniture has no single useful price without a specification, quantity and delivery scope. To budget a project imported from China, price each furniture item first, then add packing, logistics, destination charges and installation. The worked example below shows that calculation with clearly labelled hypothetical inputs.
The six cost drivers
- Specification level — material, hardware, mechanism and finish quality. The largest single factor, capable of changing price two- or three-fold within the same product category.
- Quantity — unit cost falls with volume, but not linearly. The drop is largest between a sample order and a container-scale order.
- Customisation — non-standard sizes, colours and configurations add tooling, setup and production time.
- Packing method — knock-down packing reduces volume and freight but increases site assembly; crated joinery does the opposite.
- Freight and duty — sea versus air, container utilisation, port and clearance costs, inland delivery.
- Site costs — installation labour, unloading, storage, and rework caused by late or incomplete information.
Where the money actually goes
On a typical open-plan office floor, workstations and seating account for the majority of the furniture value, with storage and meeting room furniture following. Executive areas and reception joinery usually represent a small share of quantity but a disproportionate share of value per unit.
This is why specification strategy matters. Spending the finish budget on the visible floors and keeping the operational floors on a disciplined, consistent specification produces a better result than upgrading everything uniformly.
Budgeting method for an imported package
Budget the delivered cost, not the ex-works price. A practical structure is: product cost, plus packing, plus freight to port, plus insurance, plus duty and clearance, plus inland delivery, plus installation. Each of those lines is real and each will surprise a project that omitted it.
| Cost line | What it depends on |
|---|---|
| Product | Specification, quantity, customisation |
| Packing | Knock-down versus crated, protection level |
| Freight | Volume, weight, port pair, sailing frequency |
| Insurance | Declared value and route |
| Duty and clearance | Destination country, tariff classification, documentation |
| Inland delivery | Distance, access, unloading equipment |
| Installation | Category, complexity, labour availability at site |
Worked budget: 100 workstations and 100 task chairs
Arithmetic example only, prepared 24 October 2026 in USD. Assume 100 workstations, each 1400 × 700 × 750 mm with a 25 mm laminated engineered-wood top, steel frame and fabric desktop screen, plus 100 mesh task chairs with adjustable arms. Assume product rates exclude export packing and all logistics. Power modules, storage, reception furniture and meeting tables are outside this example.
| Budget line | Hypothetical calculation | USD |
|---|---|---|
| Workstations | 100 × $160 | $16,000 |
| Task chairs | 100 × $70 | $7,000 |
| Export packing | Assumed separate allowance | $1,200 |
| Independent pre-shipment inspection | Assumed optional service allowance | $500 |
| China inland transport and export handling | Assumed allowance | $600 |
| Sea freight | Assumed allowance; route and packed volume not priced | $2,400 |
| Cargo insurance | Assumed allowance | $150 |
| Destination port and broker charges | Assumed allowance; excludes duty and taxes | $800 |
| Inland delivery to site | Assumed allowance | $900 |
| Installation | Assumed allowance | $1,500 |
| Illustrative subtotal before import duty and taxes | Sum of the lines above | $31,050 |
| Cost per furnished workstation before import duty and taxes | $31,050 ÷ 100 desk-and-chair positions | $310.50 |
Turn the example into a comparable project budget
- Issue the same BOQ revision, quantities and specification to each manufacturer; record any material or hardware deviations.
- Ask for packed carton dimensions, carton count, total cubic metres and gross weight before comparing freight allowances.
- Record the named Incoterms rule, edition and place or port. Mark every cost already included in that quotation so it is not added twice.
- Ask the destination broker to confirm classification, customs value, applicable duty, tax treatment and clearance charges for the actual goods.
- Confirm unloading, installation, floor access and any storage separately. Compare the same delivery scope, currency, quote validity and shipment date.
Why no supplier can give one rate per workstation
A rate per workstation only means something when the specification is fixed. Otherwise it is an average of a range that may span several multiples. A credible supplier will ask for the specification and quantities and then quote; a supplier that quotes immediately without them is quoting a guess.
Getting a real number
Send your BOQ or specification with quantities and your destination city. A costed, line-by-line quotation against a defined scope is the only figure that can be compared, budgeted and later checked against what was delivered.
How this guide was prepared
Prepared from the cost headings used to compare furniture quotations. The worked example was added on 24 October 2026 and uses hypothetical figures, not customer data, observed market rates or a GulfForma quotation. Import duty and taxes are left unpriced for the destination-specific calculation.