For a phased HYC01 installation, define a complete supported arrangement for each handover rather than ordering all extensions against one eventual layout. HYC01-A is listed with steel legs and HYC01-B as an extension; both have a 1200 × 1200 × 1030 mm catalogue envelope. Equal dimensions do not make the two versions interchangeable at a temporary end position.
Catalogue dimensions
| Catalogue reference | Listed L × W × H (mm) |
|---|---|
| HYC01-A(With steel legs) | 1200 × 1200 × 1030 |
| HYC01-B(Extension) | 1200 × 1200 × 1030 |
Draw the first phase as an independent installation
Mark the furniture that must be usable on the first handover date and show its temporary ends. A future extension may rely on a connection or support that has not yet been installed. Ask the supplier to identify the starter, extension and closing components for that first arrangement, including any items needed only during the temporary phase.
For example, two departments opening on different floors should be reviewed as two separate assemblies. Do not treat an extension allocated to the second floor as supported merely because a starter exists somewhere else in the order. The approved assembly drawing, rather than a summed unit count, should determine the support schedule.
Price the change from the temporary end to the final run
Overlay the final plan on the first-phase drawing. Identify which end supports remain, which move and which additional connectors or screens are needed. Request separate lines for reusable furniture, new extension parts and any labour to alter the first installation. This makes the second-phase quotation comparable without assuming that every temporary component can be reused.
Label parts and cartons by phase and room. If later-phase pieces arrive with the first shipment, identify an appropriate storage area and maintain the component labels; the catalogue footprint is not a packed-carton measurement.
Coordinate services at both handovers
The 1030 mm dimension is the listed overall height, not a confirmed worktop height. Obtain a section showing the working surface and screens, then locate sockets and cable routes for each phase. For a UAE or Saudi Arabia project, state who provides and tests the site electrical connections and whether the second installation must occur while nearby desks remain occupied.
Questions before ordering
Can HYC01-B stand at the end during phase one?
Its row identifies an extension. Have the supplier confirm the temporary end support and stability arrangement before assigning that position.
Should all phases use one BOQ quantity?
Use phase and room subtotals with a consolidated order summary. Keep starter and extension references visible in every subtotal.
Does a future extension need its own service route?
Show the intended future outlet and cable connections on the final plan and agree how they will be accessed without dismantling occupied positions.
What to include in the quotation request
- First-phase and final assembly drawings
- Starter, extension and temporary-end component lists
- Carton labels and storage allocation by phase
- Separate installation dates and service responsibilities
Catalogue basis and confirmation
The model and dimension table is based on the 2026 Yiwan English catalogue, Huanying. Confirm the selected configuration on the supplier drawing and written specification. Catalogue illustrations describe product designs and do not establish completed GulfForma projects.